2010 | 20 | 2 | 77-90

Article title

Generalization of the critical chain method supporting the management of projects with a high degree of uncertainty and imperfect information

Authors

Selected contents from this journal

Title variants

Languages of publication

EN

Abstracts

EN
In the critical chain method the fundamental notion is the project buffer, and its length is based on task estimation risk. This estimation is almost never unequivocal. If it is not correct, the whole method may turn out to be ineffective. Different experts may have different opinions about this risk. The critical chain method allows to take into account the opinion of only one expert, which may seriously falsify the image of the project situation. This paper proposes a generalization of the critical chain method allowing the use of the opinions of several experts – both while planning a project and while controlling it. Thanks to such an approach, in each phase of project planning and control we are aware of the opinions of various experts as to the correctness of the deadline which was agreed upon with the customer, as to the chances of meeting this deadline and as to the necessity of strengthening project control or introducing changes into the project.

Year

Volume

20

Issue

2

Pages

77-90

Physical description

Contributors

author
  • Institute of Organisation and Management, Wrocław University of Technology, ul. Smoluchowskiego 25, 50-372 Wrocław, Poland
  • Department of Management, Gen. Tadeusz Kościuszko Military School of Higher Education, ul. Czajkowskiego 109, 51-150 Wrocław, Poland

References

  • CHEN S.-P., Analysis of critical paths in a project network with fuzzy activity times, European Journal of Operational Research, 2007, 183(1), 442–459.
  • GOLDRATT E., Critical Chain, North River Press, Great Barrington, 1997.
  • HERROELEN W.S., LEUS R., On the merits and pitfalls of critical chain scheduling, Journal of Operations Management, 2001, 19, 559–577.
  • ICMELI O., ROM W.O., EKSIOGLU S.D., An investigation of buffer sizing techniques in critical chain scheduling, European Operations Research, 2006, 172, 401–416.
  • KUCHTA D., The critical chain method in project management – a formal description (in Polish), Badania Operacyjne i Decyzje, 2004, 1, 37–51.
  • KUCHTA D., Metoda łańcucha krytycznego w zarządzaniu projektem (in Polish), [in:] Błaszczyk T., Kuchta D., Szweda F., Trzaskalik T., Tync Ł., Wybrane zagadnienia zarządzania projektami, Seria: Informatyka w badaniach operacyjnych pod red. T. Trzaskalika, Prace Naukowe Akademii Ekonomicznej w Katowicach, Katowice, 2005, 99–118.
  • KUCHTA D., Czas i koszty w projekcie – Wybrane metody planowania i kontroli realizacji projektów (in Polish), 2010, submitted to the Publisher.
  • TUKEL O.I., ROM W.O., EKSIOGLU S.D., An investigation of buffer sizing techniques in critical chain scheduling, European Journal of Operational Research, 2006, 172(2), 401–416

Document Type

Publication order reference

Identifiers

YADDA identifier

bwmeta1.element.desklight-bd583e88-a8fd-4cb6-83b3-44bd1ac02c74
JavaScript is turned off in your web browser. Turn it on to take full advantage of this site, then refresh the page.