2011 | 1 | 2 | 183-194

Article title

Earned Value Management a budżetowanie elastyczne kosztów projektu

Selected contents from this journal

Title variants

EN
EARNED VALUE AND FLEXIBLE COST BUDGETS FOR PROJECT

Languages of publication

PL

Abstracts

EN
The paper presents a comparison of Earned Value (EV) and Flexible Budgeting (FB) in terms of managing project cost. Key performance indicators of cost efficiency characteristic of both methods have been described. Similarities and differences in the approach to the interpretation of schedule variance with relation to base-line budget (EV) and volume variance with respect to static budget (FB) have been emphasized. The significance of budgeted cost of work performed (BCWP, i.e. the earned value) and first flexible budget (FB I) as well as the nature of cost variance in the EV method vs. usage variance and price variance in flexible budgeting have been discussed. Issues of ex ante estimate-to-completion in the earned value method and ex post analytical advantages of cost control of flexible budgeting have also been addressed. In order to enrich the comparison simulation data for a hypothetical project have been applied in the article.

Contributors

  • Uniwersytet Gdański, Wydział Zarządzania, Katedra Rachunkowości

References

Document Type

Publication order reference

Identifiers

YADDA identifier

bwmeta1.element.desklight-e383d392-bded-452c-96f3-50fbc86f8d42
JavaScript is turned off in your web browser. Turn it on to take full advantage of this site, then refresh the page.