2023 | 68 | 4 (411) | 68-81

Article title

Budowa Muzeum Historii Polski - najdroższa inwestycja w obszarze kultury

Content

Title variants

EN
Construction of the Museum of the Polish History – the Most Expensive Investment in the Area of Culture

Languages of publication

Abstracts

EN
The construction of the headquarters of the Museum of the Polish History (Polish: Muzeum Historii Polski) has become one of the longest investments in the area of culture financed from the state budget, and probably one of the most expensive. It took seventeen years from the establishment of the Museum in 2006 to the termination of the construction works in 2023, and the costs of the project implementation (including the permanent exhibition) will exceed PLN 1.2 billion. By 2015, the support for the construction of the permanent headquarters of the Museum was provided through earmarked subsidies for financing or co-financing of the investment’s costs. While in 2015, the Council of Ministers took a decision to create the multiannual programme “Construction of the Museum of the Polish History” that was modified three times (in 2017, in 2018 and in 2021). The initiative was audited by the Supreme Audit Office twice. In 2015, NIK conducted the audit “Construction of museums in Poland in the years 2007–2015” which examined, among others, the construction of the headquarters of the Museum of the Polish History. In 2022, NIK carried out the planned audit “Construction of the Museum of the Polish History”, exclusively dedicated to this very investment. The question that defined the main objective of the audit read: “Was the construction of the headquarters and the permanent exhibition of the Museum of the Polish History properly prepared and realised?”. The results of the audit, which covered the years 2016–2022 (by the date of terminating the proceedings) were presented in the post-audit statement approved by the President of NIK on 12 January 2023. The article presents the main findings of the audit, referring also to the 2015 results.
PL
Budowa siedziby Muzeum Historii Polski okazała się jedną z najdłużej trwających inwestycji w dziedzinie kultury finansowanych z budżetu państwa oraz prawdopodobnie jedną z najdroższych. Od momentu utworzenia Muzeum w 2006 r. do czasu zakończenia prac budowlanych w 2023 r. upłynęło 17 lat, a koszty realizacji projektu (wraz z wystawą stałą) przekroczą 1,2 mld zł. Najwyższa Izba Kontroli dwukrotnie – w ramach kontroli planowych w 2015 r. i w 2022 r. – sprawdzała budowę placówki, przy czym ostatnie badanie skoncentrowano wyłącznie na ocenie rzetelności przygotowania i wykonania inwestycji oraz wystawy stałej. Artykuł prezentuje najważniejsze ustalenia NIK.

Year

Volume

68

Issue

Pages

68-81

Physical description

Dates

published
2023

Contributors

author
  • Najwyższa Izba Kontroli
author
  • Najwyższa Izba Kontroli

References

Document Type

Publication order reference

Identifiers

Biblioteka Nauki
20874541

YADDA identifier

bwmeta1.element.ojs-doi-10_53122_ISSN_0452-5027_2023_1_23
JavaScript is turned off in your web browser. Turn it on to take full advantage of this site, then refresh the page.