Article title

Scheduling Resource Constrained Project Portfolios with the Principles of the Theory of Constraints

Content

Title variants

Languages of publication

EN

Abstracts

EN
The paper presents a heuristic algorithm scheduling support project portfolios. It uses goal programming method, in order to identify critical resources within the meaning of E. Goldratt Theory of Constraints. Operation of heuristics is shown in a simple example. Its practical effectiveness can only be fully assessed until the computer implementation. It is planned in AIMMS environment.

Year

Volume

137

Pages

195-205

Physical description

Contributors

References

  • A Guide to the Project Management Book of Knowledge (PMBOK 2004). 3rd Ed. Newtown Square, PA: Project Management Institute.
  • Artigues C., Michelon P., Reusser S. (2003), Insertion techniques for static and dynamic resource-constrained project scheduling. "European Journal of Operational Research", 1;149(2).
  • Ayala M., Artigues C. (2010), On integer linear programming formulations for the resource-constrained modulo scheduling problem. Technical Report 10393, LAAS-CNRS, Toulouse.
  • Brucker P., Drexl A., Mohring R., Neumann K., Pesch E. (1999), Resourceconstrained project scheduling: Notation, classification, models, and methods. "European Journal Of Operational Research" No. 1.
  • Goldratt E.M. (1997), Critical Chain. Great Barrington, MA: The North River Press.
  • Hanh Quang Le (2008), Resource-Constrained Multi-Project Scheduling with Resource Moving Time for Construction Projects in Vietnam. First International Conference on Construction in Developing Countries (ICCIDC-I).
  • Jarboui B., Damak N., Siarry P., Rebai A. (2008), A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems. "Applied Mathematics and Computation" No. 15, 195(1).
  • Merkle D., Middendorf M., Schmeck H. (2002), Ant colony optimization for resource-constrained project scheduling. "IEEE Transactions On Evolutionary Computation" Vol 6(4), 333-343.
  • Mika M., Waligora G., Weglarz J. (2005), Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models. "European Journal of Operational Research", 1;164(3), 639-668.
  • Neumann K., Zimmermann J. (2000), Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints. "European Journal of Operational Research", 1;127(2), 425-443.
  • Steyn H. (2002), Project management applications of the theory of constraints beyond critical chain scheduling. "International Journal of Project Management", 20(1), 75-80.
  • Targiel K. (2012), The method of dynamic scheduling of portfolios of projects with constrained resources, in: Modelowanie Preferencji a Ryzyko'12. t. 97, Ed. T. Trzaskalik, Studia Ekonomiczne, Zeszyty Naukowe Wydziałowe. Wydawnictwo Uniwersytetu Ekonomicznego w Katowicach, Katowice, 315-324 (in Polish).
  • Tormos P., Lova A. (2003), An efficient multi-pass heuristic for project scheduling with constrained resources. "International Journal of Production Research", 41(5), 1071-1086.

Document Type

Publication order reference

Identifiers

ISSN
2083-8611

YADDA identifier

bwmeta1.element.desklight-7c695828-3540-427e-a31b-30b94120598f
JavaScript is turned off in your web browser. Turn it on to take full advantage of this site, then refresh the page.