Realizacja sztucznego terenu "Panoramy Racławickiej"

Content

Title variants

EN
THE EXECUTION OF THE RACŁAWICE PANORAMA ARTIFICIAL TERRAIN

Languages of publication

PL EN

Abstracts

EN
The construction of the staff age began with the erection of a skeleton support structure (pillars and beams) which was then sheathed with metal sheet insulated with ’’abizol”. Next the structure was covered with a suitably thick layer of ”siporex” bound with foamed concrete; in some places, this layer was currently checked for the conformity with the picture. Later a mass of foamed concrete based on fly-ash was cast (the method was worked out by the Institute of Building Engineering, of the Wroclaw Politechniie). It can be formed and re-sculpted. The top layer was coloured and covered with sterilised sand. The terrain thus prepared was then planted with roots, bushes and grass. Eventually, the colouring of the terrain was retouched to make it match the Racławice Panorama painting. In general, the construction of the staffage was improvised and only partly based on the design.

Year

Issue

4

Pages

293

Physical description

Dates

published
1984

Contributors

  • art. plastyk, Wrocław

References

Document Type

Publication order reference

Identifiers

ISSN
0029-8247

YADDA identifier

bwmeta1.element.desklight-4ea4941c-6492-48f0-90bd-9f943b31f1c2
JavaScript is turned off in your web browser. Turn it on to take full advantage of this site, then refresh the page.